Experience
Generation
Mayor Achievements | Contractor |
Incorporation to the Existing Capacity of the Vuelta de Obligado Combined Cycle connected to Substation 500 kV Río Coronda (2TG+1TV, 800 MW). Electrical Studies of Stage I.
|
CEMSA |
Tests according to Technical Procedure Nº 4 from CAMMESA for motor-generators of Salto Thermal Power Plant (16 x 1.4 MW) and Lincoln Thermal Power Plant (Prov. Buenos Aires).
|
SO Energy |
Tests of Technical Procedure Nº 4 from CAMMESA for the access to the Mercado Eléctrico Mayorista (MEM – Wholesale electrical Market) of the Transportable Generation modules in Stand By of INDUSTRIAS JUAN F. SECCO S.A. (Bid ENARSA N° UGEE 01/2010). |
Industrias Juan F. Secco S.A. |
Loma de la Lata Thermal Power Plant., Incorporation to VT 178 MW- Closing of Combined Cycle
|
Pampa Energía S.A. |
Villa Gesell TPP, Connection of a GT of 70 MW to TRANSBA network
|
RONZA-FAINSER-Centrales de la Costa Atlántica SA |
Incorporation to the Existing Capacity of the Combined Cycles installed in Thermal Power Plants San Martín and Manuel Belgrano (2TG+1TV, 800 MW). Stage III Electrical Studies.
|
CT Manuel Belgrano y CT San Martín |
Caracoles Hydraulic Power Plant (2x60 MW), San Juan- Argentina.
|
EPSE Energía Provincial Sociedad del Estado. |
Electrical Studies for the access to Cutucu TPP to the National Interconnected System of El Salvador.
|
Cutucu Energy Central America S.A. El Salvador |
Verification tests of the requirements to participate in the Frequency Primary Regulation of El Carrizal HPP.
|
Hidrocuyo S.A. |
Analysis of the Subsinchronous Resonance (SSR) Problem on the CC of TPP Salta (600 MW) by serial compensation of the Interconnection Salta (Argentina) – Andes (SING Chile) in 345 kV
|
Termoandes S.A. |
Incorporation Studies of the 5th Unit Hydraulic Power Plant Santa Isabel to the National Interconnected System. Cochabamba, Bolivia.
|
Empresa Corani S.A. |
Modeling of speed regulator set of GT and VT equipments of the 750 MW Combined Cycle of Central Puerto. |
Central Puerto S.A. |
Installation of a Pre-processor of Power-Frequency (PPF) in El Carrizal HPP of CEMPPSA.
|
CEMPPSA, CH El Carrizal |
Electric islands and Black Start for the influence area of TRANSBA S.A in Buenos Aires Argentina |
TRANSBA S.A. |
Black Start of the Combined Cycle of 750 MW of Central Puerto S.A |
Central Puerto S.A. |